KETTLER delivered the office fully leased, with homes already available at Gasworx and more under construction.
- This building is about 29% of the planned office (derived)
- The office was delivered fully pre-leased; its cost was not disclosed
- The section inside the historic district is limited to four stories; the section outside is six stories
S9 Architecture and Smallwood designed it and Moss built it.
Implications: The two office leases remove initial lease-up risk for this building but concentrate its income. The $182 million construction financing also covers portions of the residential and retail program. It does not establish how later phases will be funded or absorbed. Track the leases and delivery dates by phase.
Key Takeaways
- A fully leased office reduces lease-up risk for one building, not for the entire district.
- This building is about 29% of the planned office (derived)
- The office was delivered fully pre-leased; its cost was not disclosed
- Underwrite later residential and retail deliveries separately from the office
Commercial Property Executive, KETTLER Wraps Up Office Phase of 6 MSF Tampa Mixed-Use, Nov. 25, 2026 (read in full)
Never miss a Signal