Affordable-housing developers are reporting higher costs and delayed projects under Build America, Buy America. CRE Daily’s November 10 summary of Bloomberg’s November 9 reporting cites public housing authorities estimating compliance-cost increases of 15%–20%. Avesta Housing reportedly abandoned a $194,000 solar installation because it could not certify component compliance. Developers described months-long waiver waits, while HUD said its backlog had been halved. These are reported experiences and estimates, not a measured premium for every project.
The underlying requirements predate this week’s reporting. HUD’s implementation was phased by funding program, product category and federal obligation date. A project’s closing date alone does not establish which requirements apply.
Housing can qualify as infrastructure. HUD’s guidance for covered housing programs treats projects with five or more units as public infrastructure, subject to applicable waivers and exemptions. It also distinguishes HUD’s obligation of funds from a grantee’s later commitment to an individual project.
Domestic-content tests differ by product. Under the federal framework, manufactured products generally must be manufactured in the United States, with domestic components accounting for more than 55% of component costs, unless another applicable standard governs. Construction materials have material-specific domestic manufacturing requirements. Our guidance: confirm the applicable manufacturing and component requirements with the supplier rather than relying on its address.
HUD provides general waivers and case-specific routes for public interest, insufficient domestic availability and unreasonable cost. The unreasonable-cost route requires the domestic-product requirement to increase overall project costs by more than 25%. The reported 15%–20% increases alone would not satisfy that numerical threshold.
Our Read
For sponsors and lenders, the useful question is which purchases remain unresolved when financing closes.
A construction budget should identify the applicable funding requirements, the classification of major products, the evidence suppliers can provide and any waiver dependency. Give each unresolved item an owner and a decision date. A contingency without an executable procurement plan leaves the schedule exposed.
Separate the cost of a compliant substitute from the cost of waiting. A replacement product might change installation requirements or delivery dates. A waiver-dependent purchase can leave a contractor unable to finalize an order. Model those possibilities separately rather than applying one percentage across the entire budget.
Lenders should distinguish an approved waiver from a planned application. Sponsors should confirm who will submit the request and what documentation is still missing before relying on relief.
The underwriting response is a documented compliance path, realistic procurement alternatives and a schedule that shows where an unresolved decision can affect completion. This is general editorial analysis, not a project-specific legal determination.
Key Takeaways
Treat reported 15%–20% increases as project experience, not a universal budget multiplier.
Resolve product classification, supplier evidence and waiver dependencies before closing.
CRE Daily, November 10, 2026, citing Bloomberg’s November 9 reporting: public housing authorities estimate 15%–20% compliance-cost increases; Avesta abandoned a $194,000 solar installation over component-certification problems; developers report months-long waiver waits and HUD says its backlog was halved. Bloomberg original was not directly accessible. https://www.credaily.com/briefs/hud-buy-america-rule-stalls-affordable-housing-projects/; HUD phased-implementation waiver: requirements vary by funding program, product category and federal obligation date. https://archives.hud.gov/initiatives/baba/6331-N-10A-BABA-Updated-Public-Interest-Phased-Implementation-Waiver-for-FY-2022-and-2023-of-Build-America-Buy-America-Provision.pdf; HUD Build America, Buy America FAQ: covered housing programs treat five-or-more-unit projects as infrastructure, subject to exemptions and waivers; federal obligation is distinct from later project commitment. https://www.hud.gov/sites/default/files/Main/documents/BABA-FAQs.pdf; Federal Register, August 23, 2023, guidance for 2 CFR 184: manufactured products generally require U.S. manufacture and more than 55% domestic component costs unless another applicable standard governs; construction materials have separate manufacturing standards. https://www.federalregister.gov/documents/2023/08/23/2023-17724/guidance-for-grants-and-agreements; HUD BABA guidance, reviewed November 11, 2026: general and project-specific waiver processes; public-interest, nonavailability and unreasonable-cost grounds. Unreasonable cost requires more than a 25% increase in overall project costs. https://www.hud.gov/hud-partners/baba
Get Buy America Puts Housing Budgets and Schedules Under Pressure in your inbox
Housing authorities report 15%–20% compliance-cost increases. Funding rules, supplier documentation and waiver timing determine the risk for each project.